PMP Formula of the Week: TCPI

PMPFormulaOTW475166460What formula is used to determine To-Complete Performance Index (TCPI)?

A. (BAC – EV) / (BAC – AC)
B. EV / AC
C. EV / PV
D. CPI / SPI

Reveal Answer

The correct answer is A.

Answer A, TCPI =  (BAC – EV) / (BAC – AC), is the correct formula.

  • BAC = budget at completion
  • EV = Earned value
  • AC = Actual Cost

Answer B, EV / AC, is the formula for Cost Performance Index (CPI) and answer C, EV / PV, is the formula for Schedule Performance Index (SPI). Answer D, CPI / SPI,  is not a recognized formula.

Related Resources
PMP Exam Prep Mobile App
Project Management White Papers

Related Courses
IT Project Management
Project Management Fundamentals
Project Management, Leadership, and Communication
PMP Exam Prep Boot Camp

PMP Formula of the Week Series

  • PMP Formula of the Week: Forecasting a Necessary CPI
  • PMP Formula of the Week: Forecasting a Necessary CPI Based on an ETC
  • PMP Formula of the Week: Ahead or Behind Schedule
  • PMP Formula of the Week: Point of Total Assumption
  • PMP Formula of the Week: Rent, Lease or Buy?
  • PMP Formula of the Week: Risky Task
  • PMP Formula of the Week: Earned Value Management Methodology
  • PMP Formula of the Week: Schedule Performance Index of 1
  • PMP Formula of the Week: TCPI