PMP Formula of the Week: Three-point Estimate

PMPFormulaOTW475166460

You are determining activity duration estimates and one of your colleagues suggests using a three-point estimate. What is the primary advantage of this method?

A. Three points, rather than one, improve the accuracy of the activity duration estimate.
B. It is always preferable to consider three opinions instead of just one.
C. The best case and worst case scenarios are factored into the estimate.
D. Team members will provide the most accurate estimates.

Reveal Answer

The correct answer is A.

Both answer C and D are components of the three-point estimate, but not the primary advantage of the method. Answer B is incorrect because three opinions may not result in three different estimates.

 

Related Resources
PMP Exam Prep Mobile App
Project Management White Papers

Related Courses
IT Project Management
Project Management Fundamentals
Project Management, Leadership, and Communication
PMP Exam Prep Boot Camp

PMP Formula of the Week Series

  • PMP Formula of the Week: Forecasting a Necessary CPI
  • PMP Formula of the Week: Forecasting a Necessary CPI Based on an ETC
  • PMP Formula of the Week: Ahead or Behind Schedule
  • PMP Formula of the Week: Point of Total Assumption
  • PMP Formula of the Week: Rent, Lease or Buy?
  • PMP Formula of the Week: Risky Task
  • PMP Formula of the Week: Earned Value Management Methodology
  • PMP Formula of the Week: Schedule Performance Index of 1
  • PMP Formula of the Week: TCPI
  • PMP Formula of the Week: Fixed-Price Incentive Fee Contract
  • PMP Formula of the Week: S-Curve
  • PMP Formula of the Week: Current Project Status
  • PMP Formula of the Week: Project Schedule Information
  • PMP Formula of the Week: Random Defective Article
  • PMP Formula of the Week: Confidence Level
  • PMP Formula of the Week: EV?
  • PMP Formula of the Week: What is BAC?
  • PMP Formula of the Week: CPI of 1.0
  • PMP Formula of the Week: Product Manufacturing Choice
  • PMP Formula of the Week: SV of 338
  • PMP Formula of the Week: Three-point Estimate


from
CERTIVIEW
Unknown at 03:32
Share

No comments:

Post a Comment

‹
›
Home
View web version

About Me

Unknown
View my complete profile
Powered by Blogger.